Washington Climbers Coalition  

Go Back   Washington Climbers Coalition > Crags > West Side - Bellingham to Beacon Rock
Register FAQ Members List Calendar Search Today's Posts Mark Forums Read

Reply
 
Thread Tools Display Modes
  #1  
Old 02-05-2005
Mark Hanna Mark Hanna is offline
WCC Member
 
Join Date: Oct 2004
Posts: 13
Default Darrington road conditions

I just wanted to express my sincere thanks to the folks at the Darrington Ranger Station (FS) for their diligence in maintaining the Clear Creek road throughout the winter slides and damage. Typically, my first few trips to the area involve more boulder yanking/windfall cutting/getting the truck unstucking than actually climbing. Despite some big time damage, they were up there last week. Their efforts are greatly appreciated by those who frequent the crags and hiking trails!

Mark Hanna
Reply With Quote
  #2  
Old 04-06-2005
Matt Perkins Matt Perkins is offline
Moderator
 
Join Date: Oct 2004
Posts: 540
Default

I just spoke to a roadway person in the Darrington office and he says that, while the road up Clear Creek has been repaired following the severe damage earlier this winter, the repair was only "temporary" and the road remains a little rough. With that, and with a significant washout remaining up by the Eightmile Creek trailhead, they are hesitant to reopen the road just yet for fear somebody will go up there and damage their car or possibly even get hurt. He assured me that they will reopen it, however - he just didn't know when.
Reply With Quote
  #3  
Old 04-21-2005
Matt Perkins Matt Perkins is offline
Moderator
 
Join Date: Oct 2004
Posts: 540
Default

Additional calls to the ranger station revealed that they had decided not to reopen the road. They say they cannot afford the necessary repair, although they also say that they are repairing other roads in the area and the guys who made the call not to maintain this one say they are sorry but they had no idea there was anything important up Clear Creek.
Reply With Quote
  #4  
Old 04-29-2005
Matt Perkins Matt Perkins is offline
Moderator
 
Join Date: Oct 2004
Posts: 540
Default

In three short weeks, we have gotten our message to the Forest Service and they have responded. The roadway supervisor called to say that they have a contractor lined up to start the repair of the Clear Creek Road next week, and that it may be reopened by the following weekend.

They must have gotten a phone call or two because he asked me three times to spread the word and tell people they could stop calling.
Reply With Quote
  #5  
Old 05-09-2005
Mark Hanna Mark Hanna is offline
WCC Member
 
Join Date: Oct 2004
Posts: 13
Thumbs up Clear Creek 2060 is OPEN

I called the ranger station today, and was informed that the road is now open! Most Excellent Indeed! Job well done to all parties involved.

MH
Reply With Quote
Reply


Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Forum Jump


All times are GMT -8. The time now is 02:09 AM.


Powered by vBulletin® Version 3.6.8
Copyright ©2000 - 2010, Jelsoft Enterprises Ltd.